Project: Water Disposal Facility

Description

We were given just 9 months to design-build-commission a truck terminal, bulk storage, pre-conditioning and high-pressure injection facility. Facility included reconditioning natural-gas generator glycol heating system, truck ticket system, flare and overhead loading racks. We also created a SMART 3-D model of the facility with full linkages to P&ID’s, as-builts, purchase records, O&M manuals and multi-year maintenance forecast and budget. All units were laser-scanned prior to shipment to ensure conformance to specifications. Installation was completed under sub-Arctic and sprint-freshet conditions to capitalize on favorable commodity price market.

Key Features

  • Modular design
  • Completed 7 months faster than competing project in same geography
  • Zero lost-time or environmental incidents
  • Separate living quarters for relief operator